Consecration DayAs the year 2000 began we knew for sure that
the Y2K bug was not going to interfere with sanctuary construction, but we were having to
wait on a process call surcharging. Once the foundation was packed down enough by
the huge mound that had been built up for just that purpose, the architects and engineers
gave the go ahead to begin construction.
Ground was broken in March 2000. The progress from May 2000 through
December 2000 is evident in the photos on the right. Once the foundation was poured
and the "red steel" began to go up it became easier with each passing day to
tell more about the shape and character of the building.
Each week, before or after worship, we got a look at the progress made during the week.
Fortunately there were very few rain delays, and just as fortunately, John Wilson,
our man on the site, kept things running smoothly. We will never be able to thank John and
Phil Bass enough for all of the responsibility they shouldered for the congregation.
Until safety considerations dictated, we were able to enter the building almost at
will and look at the work in progress, but that stopped as the year came to an end.
The year 2000 was one of great anticipation on the part of the congregation and we knew
that soon all of the hard work by all of the committees would be paying off.
The contractor, Stuart Construction, and his crews treated the structure with respect
from the very beginning. They sensed they were not building just a
building......they were building a church to the glory of God. |
|

Working the Dirt
May 2000

Steel Going Up
Aug 2000

Crane in Action
Aug 2000

Size Perspective
Aug 2000

Frame Almost Complete
Aug 2000

Looking South
Aug 2000

Roofing
Sep 2000

Brick Samples
Oct 2000

Dirt Outback from Surcharging
Oct 2000

Roof On Side View
Oct 2000 |
|

Roof On Side View
Oct 2000

Walls and Roof
Oct 2000

Taking Form
Late Oct 2000

Roof On Bricks Being Laid
Late Oct 2000

First Bricks
Late Oct 2000

Looking Inside
Late Oct 2000

Bricks Going Up Quickly
Dec 2000

Interior South to North
Dec 2000

Interior North to South
December 2000

West to East
December 24 2000 |